The project is located in Urad Rear Banner, Bayannur City, Inner Mongolia, and was approved in 2021. It comprises 64 wind turbines of 5.2 MW each and 14 wind turbines of 4.8 MW each, and has now entered commercial operation. The project is estimated to reduce approximately 1.31 million tons of CO₂ emissions per year.
Notably, the project is designed to achieve high-quality engineering standards, aiming to comply with national evaluation measures for high-quality power projects and awards in China, excelling in construction quality, documentation, commissioning, and technical-economic performance.
The project is located in Urad Rear Banner, Bayannur City, Inner Mongolia, and was approved in 2022. It comprises 40 wind turbines, each with a rated capacity of 5.0 MW, and has now entered commercial operation. The project is estimated to reduce approximately 650,000 tons of CO₂ emissions per year.
Project Highlight: The project was approved, constructed, and connected to the grid within the same year, reflecting outstanding execution efficiency and management excellence.